Monday, October 6, 2008

Week of September 29th

Happy Construction returned after being away for 10 days and will be with us until it is finished! They finished the basic frame, giving the greenhouse its shape; framed the gable ends with steel; and started covering the frame with plastic.On Tuesday, CS Garber came and set up everything to dig the well, which they did on Wednesday.
The telephone company came mid-week and opened up a trench from the greenhouse to the site of the future packing house. They ran a telephone line between the buildings, and connected the water and electric lines, and buried them all in the trench.
The geothermal trenches were completed by the end of the week.