Thursday, October 23, 2008
Sunday, October 19, 2008
Week of October 13th
Week of October 6th
Here's the building early in the week (from the lane)...
Building the Head House (entrance to the greenhouse)...
The beginnings of the cooling wall at the rear of the greenhouse...
Monday, October 6, 2008
Week of September 29th
Wednesday, October 1, 2008
Week of September 22nd
The excavator dug a trench out from the headhouse about 20 feet and then up toward the road about 130 feet. The trenches are about 5 1/2 - 6 feet deep. When completed, there will be a total of eightteen trenches coming off the main one on one side and twenty-two of them coming off the other side. These branches are each 120 feet in length. Picture a very large tree.
Once each trench was dug, we took forty 800-foot-long flexible conduit and made giant slinkeys, tying the loops together with plastic zip ties, laying the slinkeys in the bottom of the trenches. Eventually, all the slinkeys will be connected to the heat pumps in the greenhouse.